Renovating while running a career: 7 things you need before your builder starts

Nicole Darragh, founder of Summit Residential, smiling at a timber table in front of a colourful painting

Most renovations don't go wrong on site. They go wrong in the inbox. A question from the builder sits unanswered while you're in back-to-back meetings. A variation gets approved on your phone between calls. A decision you thought was made turns out to be nobody's.

If you're running a demanding career, the renovation becomes a second job you never applied for. The way to stop that happening is to set the project up properly before the builder starts.

Here are the seven things I make sure every client has in place.

1. A written brief you and your partner have both signed off

A surprising number of variations start at home. One of you assumed an island bench, the other assumed a butler's pantry. Nobody wrote it down, so the builder hears two answers.

Put the brief in writing: what you're building, how you'll use each space, what matters most and what you'll trade off if the budget gets tight. Then both sign it. When a question comes up mid-build, the brief answers it, not a late-night debate.

2. A budget in five parts, not one number

"We've got $600,000" isn't a budget. It's a hope. Split it into five parts:

  1. The building contract: the builder's price, including provisional sums and prime cost allowances.
  2. Design and consultants: architect or designer, engineer, surveyor and any specialist reports.
  3. Approvals and certification: council or certifier fees and related costs.
  4. Everything outside the contract: landscaping, window coverings, furniture, appliances you're buying yourself, moving and temporary accommodation.
  5. Contingency: at least 10% of the construction cost, more for older homes.

When the budget is in parts, you can see exactly where pressure is building, and you don't raid the contingency to pay for things you simply forgot.

3. Someone whose only job is your side

Everyone on your project works for someone. Your builder runs their business. Your architect works to their scope. Your certifier checks compliance. None of them is there just to look after your interests.

When you have a full-time job, you need someone who does: reviewing quotes and the contract, checking progress claims before you pay them, and making sure decisions land with you at the right time. That's what an owner's representative does. I work only for owners, and I don't take referral fees or commissions from builders, consultants or suppliers.

Living overseas? Read 7 mistakes Australians make renovating their Sydney home from overseas.

4. A selections calendar

Tiles, tapware, appliances, lighting, joinery finishes, paint colours. Every one of these has a date by which the builder needs your decision. Miss it and the job stalls, or the builder picks something to keep moving.

A selections calendar lists every choice you need to make, the date it's due and how long the item takes to arrive. Line it up with the build program, then book the time in your own diary. Make as many choices as you can before construction starts. Decisions made on site, under pressure, are the expensive ones.

5. Builder quotes compared on inclusions and exclusions

The cheapest quote is often just the least complete one. Before you compare totals, compare what's in each quote and what isn't.

Look at:

  • Allowances: are provisional sums and prime cost items realistic, or set low to make the price look sharp?
  • Exclusions: site costs, demolition, landscaping and council fees are common gaps.
  • Assumptions: has the builder assumed no rock, no asbestos or easy access?

Put the quotes side by side on the same scope. The difference between them is usually smaller, or bigger, than the totals suggest.

6. A running variations total

A variation is any change to the contract, and almost every one changes the price. Individually they look small. Together they're where budgets go.

Keep one running total, updated every time a variation is approved. Every change should be written, priced and approved by you before the work happens. If you always know the number, you can make a calm call on the next upgrade instead of discovering the damage at the final invoice.

7. One weekly report: what's changed and what needs you

You don't have time to read 40 emails and scroll through 200 site photos. You need one update a week that tells you two things: what has changed, and what needs you.

A good weekly report covers progress against the program, any issues, variations and costs, and the decisions coming up with their deadlines. It should take five minutes to read. If it takes longer, the report isn't doing its job.

Set it up before the first day on site

All seven of these are easy to put in place before construction starts, and hard to fix once it's underway. That's when you have the most leverage and the most options.

My Project Diagnostic is a fixed-fee review of your budget, timing and key risks, so you start with a clear picture. If you're planning a renovation and your diary is already full, request a complimentary call or message me on WhatsApp.

FAQs

How much time does a renovation take for the owner?

More than most people expect, especially around design, contract signing and fit-out selections. Good setup and weekly reporting keep it to a manageable few hours a week.

What should a renovation budget include?

The building contract, design and consultant fees, approvals, everything outside the contract, and a contingency of at least 10%.

Do I need an owner's representative if I already have an architect?

It depends on your architect's scope. Many architects don't manage costs, progress claims or variations day to day. An owner's representative works only for you across the whole project.